Taylor Concrete

20475 Old Rome State Road, Watertown, New York 13601   Phone: 315-788-2191   Fax: 315-788-1591

 GEOGRID INSTALLATION  
 
    
 
 
  1. For each course requiring geogrid, lay the geogrid  horizontally on reinforced fill and on top of the previous course of units.
  2. After the geogrid is in place, install the next course of units.
  3. Pull the geogrid taut as approved by the construction engineer. Geogrid shall be laid at the proper elevation and  orientation as shown on the construction drawings or as directed by  the construction engineer.
  4. Geogrid shall be laid at the proper elevation and orientation as shown on the construction drawings or as directed by the construction engineer.
  5. Correct orientation (roll direction) of the geogrid must  be accomplished and its orientation should be verified by  the construction engineer.
  6. Follow the manufacturer's guidelines relative to  overlap requirements of uniaxial and biaxial geogrids.
  7. Operate only hand-operated compaction equipment  within three feet of the wall face.
  8. Place the reinforced fill near the wall first - then outward  to insure that the geogrid remains taut from the wall outward.
  9. Backfill material should be placed in 6" lifts and  then compacted to 95% proctor.
  10. Do not operate tracked construction equipment directly  on the geogrid. A minimum backfill thickness of 6" is  required prior to operation of tracked vehicles over the geogrid.  The turning of tracked vehicles should be kept to a minimum.
  11. Equipment, with rubber tires, may pass over the  geogrid reinforcement at slow speeds, less than 10 mph.