 SUCCESSIVE COURSES  
      
  1. Lay up the succeeding courses making sure that the  anchor bar of each unit on the upper course is laid against  the backside of the two faces of the lower course.
 
      
  1. Center the upper unit above the two lower units, and  pull forward as far as possible. The anchor bar will prevent  the upper unit from coming too far forward.
 
 
    
 
  1. After each course is complete, fill all cavities with unit  fill and compact. Unit fill should be used 12" behind the unit  as well as in the openings between the units. Do not install  an additional course without backfilling the previous  course

    Continue installing each successive course, first by  carefully placing and aligning each unit and then by backfilling  with unit fill.

    If geogrid is required, follow the instructions for  geogrid installation as per construction drawings, per  manufacturer's guidelines or per consulting engineer.